Daily Question #2700
A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.
Which risk management process should be performed?
Answers:
a. Plan Risk Responses, to outline the possible options to bypass the system performance issue.
b. Perform Qualitative Risk Analysis, to assess the extent of the system performance impact.
c. Monitor Risks, to install system performance monitoring tools and update the risk register.
d. Perform Quantitative Risk Analysis, to outline the details of the system performance issues.
A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.
Which risk management process should be performed?
Answers:
a. Plan Risk Responses, to outline the possible options to bypass the system performance issue.
b. Perform Qualitative Risk Analysis, to assess the extent of the system performance impact.
c. Monitor Risks, to install system performance monitoring tools and update the risk register.
d. Perform Quantitative Risk Analysis, to outline the details of the system performance issues.
Daily Question #2757
A project manager works for a large global company. The project manager is leading a project where the expected business value is to improve the company's image and reputation. During the project's closing phase, the project manager realizes that there is still a negative perception of the company's brand.
What should the project manager have done to prevent this?
A project manager works for a large global company. The project manager is leading a project where the expected business value is to improve the company's image and reputation. During the project's closing phase, the project manager realizes that there is still a negative perception of the company's brand.
What should the project manager have done to prevent this?
🤔2
Training Starts Soon – You Still Have Time to Enroll!
PMP: Your key to global opportunities and career growth in a changing world!
Boost your credibility, master your leadership and earn more with PMP!
1. Military Support: Education is free for Ukrainian veterans and military personnel.
2. Flexible Payment Options: Pay in 2-3 installments for easier budgeting.
3. Early Birds: Pay in full by April, 7 for a 20% discount.
4. Self-Study: Purchase access to KnowledgeMap and study independently. The subscription costs - 9.99$/month.
5. For PMI Ukraine members: additional 10% discount.
📌 Note:
All certifications of Marathon '25 - KnowledgeMap.pm/Marathon
#pmp #pmpcertification #pmpexam #pmpprep #projectmanagement #knowledgemap
Please open Telegram to view this post
VIEW IN TELEGRAM
🔥2
What is the purpose of the CAPM Agile Methodologies Domain Mock Exam, and how can it help you prepare for the real CAPM exam?
Referer to:https://knowledgemap.pm/certifications/capm-certification/capm-exam-preparation-with-pmbok/take-capm-agile-methodologies-domain-mock-exam/
#CAPM #AgileFrameworks #MockExam
Referer to:https://knowledgemap.pm/certifications/capm-certification/capm-exam-preparation-with-pmbok/take-capm-agile-methodologies-domain-mock-exam/
#CAPM #AgileFrameworks #MockExam
KnowledgeMap
Agile Frameworks CAPM Mock Exam
Prepare for success with the Agile Frameworks CAPM Mock Exam. Test your knowledge and refresh your skills for the real exam.
👍1
Daily Question #4878
A project manager is assigned to a new project team that has several stakeholders who can have significant influence over the project outcomes. The project manager categorized the stakeholders into four different groups and wants to take into account the communication needs of the project and the project’s stakeholders.
How should the project manager handle communication?
A project manager is assigned to a new project team that has several stakeholders who can have significant influence over the project outcomes. The project manager categorized the stakeholders into four different groups and wants to take into account the communication needs of the project and the project’s stakeholders.
How should the project manager handle communication?
👍1
What are the different tools and approaches used for gathering project requirements, and how do they ensure proper tracking and management throughout the project lifecycle?
Referer to:https://knowledgemap.pm/certifications/capm-certification/business-analysis-frameworks/3-determine-how-to-gather-requirements/
#CAPM #BusinessAnalysis #ProjectSuccess
Referer to:https://knowledgemap.pm/certifications/capm-certification/business-analysis-frameworks/3-determine-how-to-gather-requirements/
#CAPM #BusinessAnalysis #ProjectSuccess
KnowledgeMap
CAPM Requirements Gathering
Master CAPM Requirements Gathering with key tools, approaches, and best practices for effective project management.
👍2
Daily Question #437
Which of the following most likely be an agenda item at all team meetings?
Which of the following most likely be an agenda item at all team meetings?
Anonymous Quiz
21%
a. Discussion of project risks
54%
b. Status of current activities
4%
c. Identification of new activities
21%
d. Review of project problems
👍1
What foundational knowledge and steps are required to apply for and pass the ISTQB CTFL certification exam?
Referer to:https://knowledgemap.pm/certifications/ctfl/certification-exam-guide-istqb-ctfl/
#CTFL #Certification #SoftwareTesting #ISTQB
Referer to:https://knowledgemap.pm/certifications/ctfl/certification-exam-guide-istqb-ctfl/
#CTFL #Certification #SoftwareTesting #ISTQB
KnowledgeMap
Apply & Pass the ISTQB CTFL Exam
Ready to pass the ISTQB CTFL exam? Gain the skills, apply with confidence, and advance your software testing career today!
👍2
Daily Question #1767
Processes of configuration management commonly include all of the following except:
Processes of configuration management commonly include all of the following except:
Anonymous Quiz
17%
a. Configuration identification.
31%
b. Configuration status accounting.
32%
c. Configuration chartering.
20%
d. Configuration audit.
👍1🤔1
What is the recommended approach for preparing for the PMP exam, according to the Learning the Process Domain?
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-exam-preparation-process-domain/
#PMP #ProjectManagement #LearningTheProcessDomain
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-exam-preparation-process-domain/
#PMP #ProjectManagement #LearningTheProcessDomain
KnowledgeMap
PMP Exam Preparation Process Domain
Master PMP exam preparation with a focus on the process domain and key study strategies for project management success.
👍3
Daily Question #2489
Which of the following is not considered an Internal Stakeholder?
Which of the following is not considered an Internal Stakeholder?
Anonymous Quiz
13%
a. Portfolio governance body
5%
b. Portfolio team
49%
c. Investors
32%
d. None of the options
👍1
What are the key steps involved in addressing and removing impediments, obstacles, and blockers for a project team, and how can a project manager ensure continuous reassessment of these challenges?
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-people-domain-preparation/1-7-pmp-certification-obstacle-resolution/
#PMP #ProjectManagement #TeamImpediments
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-people-domain-preparation/1-7-pmp-certification-obstacle-resolution/
#PMP #ProjectManagement #TeamImpediments
KnowledgeMap
PMP Certification Obstacle Resolution
Learn how to address and remove impediments, obstacles, and blockers for your team to succeed in PMP Certification Obstacle Resolution.
👍1
Daily Question #1327
Which of the following is NOT a normal result of changes to the project?
Which of the following is NOT a normal result of changes to the project?
Anonymous Quiz
8%
a. They may require new or revised activity duration estimates.
50%
b. They may require new or revised work performance reports.
8%
c. They may require new or revised activity sequence planning.
35%
d. They may require alternative schedule analysis.
👍1
What are the key steps and resources involved in validating project requirements through product delivery, as outlined in the CAPM certification materials?
Referer to:https://knowledgemap.pm/certifications/capm/business-analysis-frameworks/6-validate-requirements-through-product-delivery/
#CAPM #RequirementsValidation #ProductDelivery
Referer to:https://knowledgemap.pm/certifications/capm/business-analysis-frameworks/6-validate-requirements-through-product-delivery/
#CAPM #RequirementsValidation #ProductDelivery
KnowledgeMap
CAPM Requirements Validation Product Delivery
Learn CAPM Requirements Validation Product Delivery. Master acceptance criteria and ensure product readiness for successful project outcomes.
👍1
#ISO21502 Question #2769
The documentation that defines a proposed alteration to a project is known as:
The documentation that defines a proposed alteration to a project is known as:
Anonymous Quiz
15%
a. Corrective action
65%
b. Change request
7%
c. Preventive action
13%
d. Assumption
🤔1
What are the key activities and resources involved in effectively managing project artifacts according to the PMP certification guidelines?
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-exam-preparation-process-domain/2-12-manage-project-artifacts/
#ProjectArtifacts #PMP #Certification #ProjectManagement
Referer to:https://knowledgemap.pm/certifications/pmp/pmp-exam-preparation-process-domain/2-12-manage-project-artifacts/
#ProjectArtifacts #PMP #Certification #ProjectManagement
KnowledgeMap
PMP Manage Project Artifacts
Improve your PMP skills: Understand how to manage project artifacts, ensure accuracy, and boost effectiveness.
👍3
#PMP Question #5265
Stakeholders in some industries prefer to deal with programmers and system analysts directly, bypassing project managers. This complicates managing resources on projects.
How should a project manager solve this issue?
Stakeholders in some industries prefer to deal with programmers and system analysts directly, bypassing project managers. This complicates managing resources on projects.
How should a project manager solve this issue?