Daily Question #2700
A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.
Which risk management process should be performed?
Answers:
a. Plan Risk Responses, to outline the possible options to bypass the system performance issue.
b. Perform Qualitative Risk Analysis, to assess the extent of the system performance impact.
c. Monitor Risks, to install system performance monitoring tools and update the risk register.
d. Perform Quantitative Risk Analysis, to outline the details of the system performance issues.
Answers #2700
Anonymous Quiz
36%
a
38%
b
8%
c
18%
d
👍2😨1
Daily Question #2757
A project manager works for a large global company. The project manager is leading a project where the expected business value is to improve the company's image and reputation. During the project's closing phase, the project manager realizes that there is still a negative perception of the company's brand.
What should the project manager have done to prevent this?
🔔Join Our April Group of 🔤🔤🔤 Prep!
Training Starts Soon – You Still Have Time to Enroll!

ℹ️About the Preparation Course:
Price: €790⭐️
Duration: 3 months
Certification: Earn a certificate for 35 hours of study.
Full access to the KnowledgeMap platform included.

We will be holding an open onboarding on April, 7 at 16:00GMT.
🔗Join us: https://calendar.app.google/ivtsDWeDgHYwbmXN7

PMP: Your key to global opportunities and career growth in a changing world!
Boost your credibility, master your leadership and earn more with PMP!


Got Questions? Ask @AnatoliiSavin! Founder & Chief Mentor of KnowledgeMap is here to guide your certification journey. Reach out for expert advice and personalized mentoring!

⭐️ Ways to Save 💰:
1. Military Support: Education is free for Ukrainian veterans and military personnel.
2. Flexible Payment Options: Pay in 2-3 installments for easier budgeting.
3. Early Birds: Pay in full by April, 7 for a 20% discount.
4. Self-Study: Purchase access to KnowledgeMap and study independently. The subscription costs - 9.99$/month.
5. For PMI Ukraine members: additional 10% discount.


📌 Note: 📣
The next individual PMP Prep group begins on May 19, 2025.
The PMI-PBA group starts on April 21, and the PMI-ACP group starts on May 5.
All certifications of Marathon '25
- KnowledgeMap.pm/Marathon

#pmp #pmpcertification #pmpexam #pmpprep #projectmanagement #knowledgemap
Please open Telegram to view this post
VIEW IN TELEGRAM
🔥2
Daily Question #4878
A project manager is assigned to a new project team that has several stakeholders who can have significant influence over the project outcomes. The project manager categorized the stakeholders into four different groups and wants to take into account the communication needs of the project and the project’s stakeholders.
How should the project manager handle communication?
Daily Question #437
Which of the following most likely be an agenda item at all team meetings?
Anonymous Quiz
21%
a. Discussion of project risks
54%
b. Status of current activities
4%
c. Identification of new activities
21%
d. Review of project problems
👍1
Daily Question #1767
Processes of configuration management commonly include all of the following except:
Anonymous Quiz
17%
a. Configuration identification.
31%
b. Configuration status accounting.
32%
c. Configuration chartering.
20%
d. Configuration audit.
👍1🤔1
Daily Question #2489
Which of the following is not considered an Internal Stakeholder?
Anonymous Quiz
13%
a. Portfolio governance body
5%
b. Portfolio team
49%
c. Investors
32%
d. None of the options
👍1
#ISO21502 Question #2769
The documentation that defines a proposed alteration to a project is known as:
Anonymous Quiz
15%
a. Corrective action
65%
b. Change request
7%
c. Preventive action
13%
d. Assumption
🤔1
#PMP Question #5265
Stakeholders in some industries prefer to deal with programmers and system analysts directly, bypassing project managers. This complicates managing resources on projects.
How should a project manager solve this issue?