The Russian JSC “Soyuzparfumerprom Mobile Mechanized Column” (claimant), as buyer, and an Italian manufacturer (respondent), as supplier, entered into an agreement for the supply of equipment to Russia (the Agreement). The Agreement contained an arbitration clause providing for arbitration under the Rules of the Arbitration Institute of the Stockholm Chamber of Commerce (SCC).
In early 2022, the respondent informed the claimant that it was unable to perform its contractual obligations due to force majeure and declared the Agreement terminated. Disagreeing with the respondent’s actions, the claimant commenced SCC arbitration. The arbitral tribunal ruled in favor of the respondent, finding that the termination was lawful due to the existence of valid force majeure circumstances.
The claimant applied to the Svea Court of Appeal to set aside the award, arguing that:
The Svea Court of Appeal rejected the claimant’s arguments and upheld the award, relying on the following considerations:
Accordingly, the Svea Court of Appeal refused the Russian claimant’s application to set aside the arbitral award.
TRANSLATED BY AI
Original see here
Please open Telegram to view this post
VIEW IN TELEGRAM
Schlumberger Logelco, Inc., Panama, as contractor (applicant), and Chepakovskoye Oil Production Enterprise LLC, as customer (respondent), entered into an agreement for integrated services, including engineering and technical support for the construction of wells with horizontal completions at the Chepakovskoye field in the Stavropol Region. Under the agreement, if the contractor’s equipment was lost in a well, the customer was required to pay the contractor the full replacement cost of equivalent new equipment. The agreement also contained an arbitration clause in favor of the ICAC at the Chamber of Commerce and Industry of the Russian Federation.
Following an incident that made it impossible to retrieve the equipment from the well, the applicant commenced arbitration. The arbitral tribunal partially upheld the applicant’s claims, ordering the respondent to pay more than RUB 60 million in property losses and USD 30,000 in registration and arbitration fees.
The applicant applied to the Stavropol Region Arbitrazh (Commercial) Court for a writ of execution for compulsory enforcement of the arbitral award. The respondent objected, relying on the following grounds:
The court rejected the respondent’s arguments and issued a writ of execution for the award. The respondent appealed the first-instance ruling to the North Caucasus District Commercial Court, reiterating the same arguments.
The North Caucasus Circuit Arbitrazh (Commercial) Court likewise rejected the respondent’s arguments, relying on the following considerations:
Accordingly, the court found no grounds to set aside the first-instance ruling and dismissed the respondent’s cassation appeal.
TRANSLATED BY AI
Original see here
Please open Telegram to view this post
VIEW IN TELEGRAM
Telegram
Международный арбитраж
⚖️ Суд округа подтвердил, что факт регистрации кредитора в «недружественном» государстве не ведет автоматически к отказу в признании и приведении в исполнение третейского решения в его пользу
Компания Schlumberger Logelco, Inc., Панама, в качестве исполнителя…
Компания Schlumberger Logelco, Inc., Панама, в качестве исполнителя…
A Russian company, as buyer (claimant), and a German company, as seller (respondent), entered into a sales agreement for equipment in 2021. The agreement provided for three deliveries and contained an arbitration clause in favor of the ICAC at the Chamber of Commerce and Industry of the Russian Federation. The first two deliveries were duly performed; however, following the events of February 2022, the respondent failed to make the third delivery.
The claimant commenced arbitration under the ICAC Rules. The arbitral tribunal rendered an award in the claimant’s favor, ordering the respondent to pay more than EUR 186,000 plus interest.
The claimant subsequently applied to the Higher Regional Court of Stuttgart for recognition and enforcement of the award in Germany. The court held that, at that time, enforcement of the award would conflict with sanctions imposed on Russian persons and, consequently, with German public policy, and dismissed the application.
In the course of the proceedings, the respondent applied for an order requiring the claimant to provide security for costs by depositing funds with the court. Under German law, such security may be required from a party to proceedings that is not resident in an EU Member State in order to ensure the opposing party’s ability to recover legal costs. However, this rule does not apply where an international treaty provides otherwise.
The issue of security for costs in this case was governed by the 1954 Hague Convention on Civil Procedure (the Convention), to which both Russia and Germany are parties. Article 17 of the Convention prohibits requiring security solely on the ground of a party’s foreign nationality. The court therefore dismissed the respondent’s application.
Disagreeing with the refusal to recognize and enforce the arbitral award, the claimant appealed the first-instance decision to the Federal Supreme Court of Germany.
In the same proceedings before the Federal Supreme Court, the respondent again sought security for costs, relying on the following arguments:
The Federal Supreme Court rejected both arguments, holding that:
Accordingly, the Federal Supreme Court of Germany held that there were no grounds to require the Russian company to provide security for costs on the basis of its nationality.
TRANSLATED BY AI
Original see here
Please open Telegram to view this post
VIEW IN TELEGRAM
In 2005, SPAO Ingosstrakh (the interested party) and Tahoma Enterprises Ltd. (the shipowner, Nigeria) entered into a shipowner's civil liability insurance contract, which also covered liability for cargo. Under the terms of the contract, all disputes were to be resolved by the Maritime Arbitration Commission (MAC) at the Chamber of Commerce and Industry of the Russian Federation.
In 2006, Gales Maritime Inc. (charterer) contracted with the shipowner to carry frozen fish to Nigeria for consignee Fiogret Ltd. (applicant). During a port call in Liberia, a fire damaged part of the cargo, leading the applicant to sue the shipowner and charterer in the Federal High Court of Lagos. The interested party was initially a defendant, then removed, and later joined as a third party, enabling enforcement against its assets.
In 2008, the court awarded over USD 1.6 million in damages to the applicant against the shipowner and charterer (Judgment No. 1), and simultaneously awarded the same amount in insurance indemnity against the interested party in favor of the shipowner and charterer (Judgment No. 2). The claim against the interested party was later assigned to the applicant for USD 1.
The applicant applied to the Arbitration Court of the City of Moscow for recognition and enforcement in Russia of Judgment No. 2. Among other things, the applicant stated that the Nigerian court had jurisdiction because the applicant was not a party to the arbitration agreement in favor of the MAC at the Chamber of Commerce and Industry of the Russian Federation. The applicant also argued that the three-year time limit for seeking recognition and enforcement had not expired, since Judgment No. 2 had only become final after the Supreme Court of Nigeria upheld it in 2021.
The interested party objected to the enforcement of the Nigerian judgment, relying inter alia on the following arguments:
During the proceedings, the parties submitted expert opinions on Nigerian law that conflicted with each other. Upon the parties' motion, the court sent a request for an opinion to the Ministry of Justice of Nigeria, whose conclusions on 10 issues were set out in detail in the court's ruling. The opinion contains findings based on the 1958 New York Convention. The opinion has it all: we learned what Fi-Fa means (not football-related), that Nigeria has sheriffs, brushed up on French legal terms, and read American precedents. We are confident that the judge of the Arbitration Court of the City of Moscow is now fully armed to pass an exam on Nigerian procedure.
Having become well-versed in Nigerian law, the Arbitration Court of the City of Moscow rejected the applicant's arguments, relying primarily on the following grounds:
As a result, the Arbitration Court of the City of Moscow refused to recognize and enforce the Nigerian court judgment in Russia.
TRANSLATED BY AI
Original see here
Please open Telegram to view this post
VIEW IN TELEGRAM
Telegram
Международный арбитраж
⚖️ Суд отказал в признании решения нигерийского суда, вынесенного почти 20 лет назад – процессуальное право Нигерии в деталях
В 2005 году СПАО «Ингосстрах» (заинтересованное лицо) и Tahoma Enterprises Ltd. (судовладелец, Нигерия) заключили договор страхования…
В 2005 году СПАО «Ингосстрах» (заинтересованное лицо) и Tahoma Enterprises Ltd. (судовладелец, Нигерия) заключили договор страхования…
The United Nations Commission on International Trade Law (UNCITRAL), at its 59th annual session in New York, adopted a series of instruments aimed at simplifying the recognition and enforcement of arbitration awards in electronic form and facilitating electronic communications in international commercial arbitration. The package was prepared by Working Group II on Dispute Resolution as part of the project on the digital economy, based on an initiative put forward by Japan in 2024, as well as proposals from Bahrain, Switzerland and Mexico.
The amendments were introduced through “soft law” rather than by amending the New York Convention itself, as such a measure would have required the consent of all 170 States parties to the Convention.
Under the adopted recommendation, the New York Convention should be interpreted so that a national court may not refuse recognition and enforcement of an arbitration award solely on the ground that the award is in electronic form.
The following amendments were also made to the UNCITRAL Model Law:
The updated UNCITRAL Notes on Organizing Arbitral Proceedings instruct arbitral tribunals to consult with the parties in advance when issuing an arbitration award in electronic form regarding any specific requirements or restrictions applicable in the jurisdiction where enforcement of the award is contemplated.
UNCITRAL Chair Ann-Jouban Bré emphasized that the amendments “respond to the trend towards the digitalization of trade and build on UNCITRAL’s existing framework for electronic commerce, ensuring interoperability between the existing architecture of arbitration regulation and the digital economy.”
TRANSLATED BY AI
Original see here
Please open Telegram to view this post
VIEW IN TELEGRAM
Globalarbitrationreview
UNCITRAL eases enforcement of awards in electronic form
As it marks its 60th year, UNCITRAL has adopted a recommendation on the interpretation of the New York Convention and amendments to its Model Law on international commercial arbitration that will make it easier for parties around the world to secure recognition…
🔥1
A contract was concluded between Vitoil Limited Company (the Company), United Kingdom, and SIBET FZCO (the Claimant), UAE. To secure the Company’s obligations under the main contract, a guarantee agreement was also concluded between the Claimant and a Russian individual (the Interested Party). The guarantee agreement contained an arbitration clause in favor of DIAC.
Since the Company failed to perform its obligations, the Claimant initiated DIAC arbitration proceedings against the Interested Party under the guarantee agreement. During the arbitration, the parties entered into a settlement agreement, under which the Interested Party was obliged to make payments to the Claimant in accordance with an approved schedule. In case of non-payment, interest at the rate of 19% per annum was also to accrue on the principal debt. The parties' settlement agreement was approved by a DIAC arbitral award on agreed terms.
The Interested Party paid only part of the established amounts; therefore, the Claimant applied to the Moscow City Court for recognition and enforcement of the DIAC arbitral award.
The Interested Party, in turn, objected to the granting of the application, arguing its position on the following grounds:
The Moscow City Court disagreed with the Interested Party’s position and relied on the following circumstances:
As a result, the Moscow City Court granted the application for recognition and enforcement of the DIAC arbitral award on the territory of the Russian Federation.
TRANSLATED BY AI
Original see here.
Please open Telegram to view this post
VIEW IN TELEGRAM
LLC "Gazprom Methanol" (the Claimant), as the customer, and LLC "Tomskneftegazproekt" (the Interested Party), as the contractor, entered into a contract for design and survey work. The contract contained an arbitration clause in favor of the Arbitration Center under the Autonomous Non-Profit Organization "NIRA TEK" (ANO "NIRA TEK")
The Claimant initiated arbitration proceedings at the Arbitration Center under ANO "NIRA TEK" seeking recovery of penalties, registration and arbitration fees, and termination of the contract. The arbitral tribunal rendered a decision fully satisfying the Claimant's claims.
The Claimant applied to the Commercial Court of the Tomsk Region for a writ of execution to enforce the arbitral award. The Interested Party objected to the issuance of the writ, citing the following circumstances:
The Commercial Court of the Tomsk Region rejected the Interested Party's arguments based on the following circumstances of the case:
Thus, the Commercial Court of the Tomsk Region issued a writ of execution for the enforcement of the arbitral award.
TRANSLATED BY AI
Original see here
Please open Telegram to view this post
VIEW IN TELEGRAM
❤2
LLC "D.N.K." (the Claimant, shipowner) and LLC "Nizhegorodskaya Logisticheskaya Kompaniya" (the Respondent, charterer) entered into 15 standard bareboat charter agreements.
The agreements contained arbitration clauses in favor of arbitration under the rules of the London Maritime Arbitrators Association (LMAA).
Notwithstanding the arbitration clauses provided for in the agreements, the Claimant filed a claim with the Commercial Court of the Nizhny Novgorod Region against the Respondent for recovery of arrears in the amount of RUB 409 million under the charter agreements.
Subsequently, the Claimant assigned its rights under the charter agreements to a Cypriot company – AAS Amur Assets Shipping Company Limited, on the basis of which the court effected a procedural substitution of the Claimant.
The Respondent filed a motion to dismiss the claim without consideration, citing the parties' agreement to refer disputes to arbitration under the rules of the London Maritime Arbitrators Association (LMAA).
In response, the Claimant argued that the arbitration clauses had not been concluded. In support thereof, the Claimant referred to the fact that the parties had used the BARECON‑2001 form for bareboat charters but had not specified in Box 35 (dispute resolution) which option they had chosen. Box 35 provides for the following options:
In addition, in the Claimant's view, the dispute could not be referred to arbitration due to the imposition of restrictive measures against Russia, which, as the Claimant alleged, restrict its access to justice in proceedings under LMAA rules in London.
The court rejected the Claimant's objections, relying on the following circumstances:
Thus, the court dismissed the Cypriot company's claim against the Russian Respondent without consideration, based on the Respondent's reliance on the arbitration clauses in the agreements.
According to the case file, today the ruling was upheld by the court of appeal. At the time of publication of this post, the decision had not yet been published.
TRANSLATED BY AI
Original see here
Please open Telegram to view this post
VIEW IN TELEGRAM
❤4
Finnish company TM System Finland Oy (claimant), as supplier, and Russian JSC ILIM Group (respondent), as purchaser, entered into a supply and services agreement as part of a project to construct a pulp and paper mill in Ust-Ilimsk. The agreement contained an arbitration clause providing for arbitration under the ICC Rules, with Geneva as the seat of arbitration.
Despite the arbitration clause, the claimant brought an action before the St Petersburg Commercial Court and Leningrad Region Arbitrazh (Commercial) Court. In support of the Russian state court’s jurisdiction, the claimant argued the following:
The court rejected the claimant’s arguments, relying on the following considerations:
Accordingly, the court held that the parties’ arbitration agreement was enforceable and that there were no grounds for establishing exclusive jurisdiction over the dispute. The St Petersburg Commercial Court and Leningrad Region Commercial Court therefore left the Finnish claimant’s action without consideration.
TRANSLATED BY AI
Original see here
Please open Telegram to view this post
VIEW IN TELEGRAM
❤2
LLC “GAMMA” (the Applicant), as the supplier, and JSC “NIKIMT-Atomstroy” (the Interested Party), as the purchaser, entered into a contract for the supply of generator units to the construction site of the El Dabaa Nuclear Power Plant in the Arab Republic of Egypt (the Contract). The Contract contained an arbitration clause providing for arbitration by the Arbitration Center at the Russian Union of Industrialists and Entrepreneurs (RSPP).
Due to the delayed payment for the goods, the Applicant commenced arbitration pursuant to the arbitration clause, seeking payment from the Interested Party of approximately RUB 20 million in outstanding amounts for the goods supplied, contractual penalties, and arbitration costs.
In the course of the arbitration, the Interested Party asserted a set-off of mutual claims arising from the Applicant’s failure to deliver the full quantity of goods and its delivery of incomplete equipment.
Under the Contract, the Applicant was required to pay the Interested Party a contractual penalty equal to 10% of the value of the incomplete goods.
The Interested Party stated that it had previously sent the Applicant a claim demanding payment of the contractual penalty, but the Applicant had failed to satisfy the claim.
The arbitral tribunal granted the Applicant’s claims in full. At the same time, the arbitrators rejected the Interested Party’s set-off argument, stating that under the applicable arbitration rules, a set-off had to be asserted in the form of a counterclaim, whereas the Interested Party had not filed a counterclaim.
As the Interested Party failed to comply with the arbitral award voluntarily, the Applicant applied to the Arbitrazh Court of the Republic of Bashkortostan for the issuance of a writ of execution for the compulsory enforcement of the arbitral award.
The Interested Party filed a counter-application seeking partial setting aside of the arbitral award on the grounds that the arbitral tribunal had refused to consider its set-off claim. According to the Interested Party, enforcement of an arbitral award rendered without taking into account the set-off/netting of mutual obligations would violate the public policy of the Russian Federation, the principles of proportionality of civil liability, and the Interested Party’s right to a comprehensive and objective consideration of the case.
The Arbitrazh Court of the Republic of Bashkortostan rejected the Interested Party’s arguments.
Accordingly, the court issued a writ of execution for the compulsory enforcement of the arbitral award.
TRANSLATED BY AI
Original see here
Please open Telegram to view this post
VIEW IN TELEGRAM
Recipe for Failure When Seeking to Set Aside an Arbitral Award:
1️⃣ Hope that the arbitrators will figure out on their own to request evidence;
2️⃣ File to set aside the award;
3️⃣ Voluntarily comply with the award on your own while the set-aside proceedings are ongoing
LLC "Sfera" (the applicant) filed a petition with the Commercial Court of the city of Moscow to set aside an award rendered by the Arbitral Institution at the Russian Union of Mechanical Engineers. The award had recovered from JSC "Tupolev" (the interested party) in favor of the applicant: RUB 20,000 in damages, RUB 1,613.25 in arbitration fees, and RUB 20,000 in legal representative costs — with the remainder of the claim dismissed.
Among other things, the applicant argued that it had been deprived of the right to a fair hearing because the arbitral tribunal had not requested necessary evidence on its own.
After examining the applicant's arguments, the Commercial Court of the city of Moscow denied the petition and upheld the arbitral award.
Referring to the arbitral institution's rules, the court stated that the arbitral tribunal has the right, but not the obligation, to invite the parties to submit additional evidence; nor is it required to obtain evidence on its own initiative if the parties themselves have not shown due diligence. The arbitral case file contained no evidence that the applicant had requested the tribunal to obtain evidence or to hold an oral hearing for that purpose.
On the contrary, the applicant neither claimed that it was unable to obtain the additional materials independently nor asked the arbitral tribunal for assistance in securing them.
The Commercial Court of the city of Moscow noted that denying a claim for lack of proof does not violate the right to judicial protection — it is simply the result of the allocation of the burden of proof, which is consistent with the principles of adversarial proceedings and party autonomy.
The court specifically emphasized that the arbitral tribunal had examined the submitted documents, assessed them, and provided specific reasons why they were deemed insufficient.
The court also took into account that the interested party had voluntarily complied with the award during the set-aside proceedings. Therefore, the court concluded that the applicant's rights in the satisfied portion had already been restored, and challenging the award as to the remainder effectively sought a substantive review of the tribunal's findings — which is impermissible.
📎 The full text of the judicial act is available here.
TRANSLATED BY AI
Original see here
LLC "Sfera" (the applicant) filed a petition with the Commercial Court of the city of Moscow to set aside an award rendered by the Arbitral Institution at the Russian Union of Mechanical Engineers. The award had recovered from JSC "Tupolev" (the interested party) in favor of the applicant: RUB 20,000 in damages, RUB 1,613.25 in arbitration fees, and RUB 20,000 in legal representative costs — with the remainder of the claim dismissed.
Among other things, the applicant argued that it had been deprived of the right to a fair hearing because the arbitral tribunal had not requested necessary evidence on its own.
After examining the applicant's arguments, the Commercial Court of the city of Moscow denied the petition and upheld the arbitral award.
Referring to the arbitral institution's rules, the court stated that the arbitral tribunal has the right, but not the obligation, to invite the parties to submit additional evidence; nor is it required to obtain evidence on its own initiative if the parties themselves have not shown due diligence. The arbitral case file contained no evidence that the applicant had requested the tribunal to obtain evidence or to hold an oral hearing for that purpose.
On the contrary, the applicant neither claimed that it was unable to obtain the additional materials independently nor asked the arbitral tribunal for assistance in securing them.
The Commercial Court of the city of Moscow noted that denying a claim for lack of proof does not violate the right to judicial protection — it is simply the result of the allocation of the burden of proof, which is consistent with the principles of adversarial proceedings and party autonomy.
The court specifically emphasized that the arbitral tribunal had examined the submitted documents, assessed them, and provided specific reasons why they were deemed insufficient.
The court also took into account that the interested party had voluntarily complied with the award during the set-aside proceedings. Therefore, the court concluded that the applicant's rights in the satisfied portion had already been restored, and challenging the award as to the remainder effectively sought a substantive review of the tribunal's findings — which is impermissible.
TRANSLATED BY AI
Original see here
Please open Telegram to view this post
VIEW IN TELEGRAM
The Investment Arbitration Subcommittee of the International Bar Association (IBA) has published a report and recommendations on the participation of third parties (i.e., persons who are not direct parties to the dispute) in investment arbitration.
The report's findings are based on a study of 135 investment arbitrations conducted up to December 11, 2024.
The report notes that third-party involvement can enhance the legitimacy and transparency of the process, as well as assist the arbitral tribunal in addressing issues affecting the public interest.
The report outlines two main areas for further work:
Based on the study's findings, the IBA concluded that arbitrators generally have the authority to accept third-party applications, even if the relevant investment treaty or rules do not expressly provide for such a possibility. However, there is no uniform approach to how this authority is exercised, particularly with regard to disclosure of information and whether arbitrators may invite third parties to submit applications ex officio.
The IBA does not provide clear recommendations on the allocation of costs when a third party participates in the proceedings, acknowledging that arbitral practice remains inconsistent.
At the same time, the IBA considers that the approach to this issue may vary depending on whether the third party joined the proceedings voluntarily or was invited to participate by the arbitral tribunal or a party.
TRANSLATED BY AI
Original see here.
Please open Telegram to view this post
VIEW IN TELEGRAM
❤1
Earlier, we reported that the Commercial Court of the city of Moscow had terminated proceedings on the issuance of a writ of execution for enforcement of an award rendered by the International Commercial Arbitration Court at the Chamber of Commerce and Industry of the Russian Federation (ICAC at the RF CCI) in favor of JSC "NORMETIMPEX" (the applicant) against JSC "Zaporozhtransformator" (the interested party). The court terminated the proceedings on the grounds that the claims under the ICAC award had already been included in the register of creditors' claims of Ukraine on the basis of a judicial act of the Kyiv Court of Appeal. The court held that, under such circumstances, the applicant was not entitled to initiate a separate enforcement proceeding.
The applicant filed a cassation appeal with the Commercial Court of the Moscow District.
The cassation court disagreed with the court of first instance and upheld the applicant's arguments. The court noted that the ICAC award cannot be enforced in Ukraine by virtue of paragraph 5 of Article 4 of Ukrainian Law No. 2116-IX of March 3, 2022 "On the Basic Principles of Compulsory Seizure in Ukraine of Property Objects Owned by the Russian Federation." This act established the compulsory seizure of Russian property in Ukraine and declared the debts of Ukrainian organizations (both state and private) to be extinguished.
The court also recognized the exclusive jurisdiction of Russian courts, citing Article 248.1 of the Russian Commercial Procedure Code, since the basis for this dispute is the restrictive measures imposed by a foreign state (Ukraine) against Russian persons.
TRANSLATED BY AI
Original see here
Please open Telegram to view this post
VIEW IN TELEGRAM
A Hong Kong-based developer (the "Developer") and a mainland Chinese holding company (the "Holding Company") entered into a cooperation agreement in 2012 for the development of land in the Fuzhou district (the "Agreement").
In 2021, the Holding Company filed a claim in the Hong Kong Court of First Instance against the Developer, alleging breach of the Agreement. The parties subsequently entered into a settlement agreement, which provided for a repayment schedule to the Holding Company, in exchange for which the Holding Company undertook to discontinue the court proceedings. The settlement agreement also contained an arbitration clause in favor of the Beijing Arbitration Commission and provided for the application of PRC law. On the Holding Company's side, the settlement agreement was signed by a person "having the ability to effectively direct the company's activities," as the Developer later stated.
Despite the settlement agreement, the Holding Company did not withdraw its claim in the Hong Kong court. In view of this, the Developer initiated arbitration and obtained an award requiring the Holding Company to terminate the Hong Kong proceedings and pay the Developer RMB 15 million in damages. In reaching this decision, the arbitral tribunal concluded that the settlement agreement had been signed on behalf of the Holding Company by an unauthorized person. Nevertheless, the agreement was binding on the Holding Company because the Developer had relied on the apparent authority of that person.
The Developer applied to the Hong Kong court for recognition and enforcement of the arbitral award. The respondent objected, arguing that the arbitration agreement was invalid due to collusion between the Developer and the signatory on the respondent's side, and that recognition of the award in Hong Kong would be contrary to public policy.
The Hong Kong Court of First Instance upheld the Holding Company's position, basing its decision on the following grounds:
In the end, the Hong Kong Court of First Instance refused the claimant's application for recognition and enforcement of the arbitral award.
TRANSLATED BY AI
Original see here
Please open Telegram to view this post
VIEW IN TELEGRAM
LLC "Bizaps" (the applicant), as the service provider, and LLC "Aller Group" (the interested party), as the customer, entered into a service agreement containing an alternative dispute resolution clause (the contract). Under the clause, the claimant could choose between a state court and an ad hoc arbitral tribunal with the well‑known arbitrator A.V. Kravtsov
Relying on an alleged debt under the contract, the applicant initiated arbitration. A.V. Kravtsov granted the claims in full
The Commercial Court of the City of the city of Moscow refused to issue the writ – a frequent outcome with Kravtsov's awards.
The court established, as a matter of course, that the arbitral tribunal exhibited objective characteristics of a permanent arbitral institution without the status of a Permanent Arbitration Institution (PAI).
The court relied, as usual, on the fact that signs of a permanent arbitral tribunal are evident from the website of the tribunal, established in 2010, with sections such as "Chairman of the Court", "Presidium", "Expert Council", and "Fees". Notably, the website offers, on a fee‑based basis, services for facilitating the enforcement of awards, including those rendered by Kravtsov himself – effectively a "turnkey" arbitration award.
Furthermore, during the arbitral proceedings, the interested party acknowledged the claims in full without any substantive objections. The court noted that this fact, in itself, does not disprove the existence of a debt, but neither does it allow the court to compensate for the lack of substantive scrutiny of the issue by the arbitral tribunal.
The Commercial Court of the City of the city of Moscow also took into account that the applicant in this case was represented by an individual who serially represents various unrelated applicants in proceedings for enforcement of Kravtsov's awards.
Thus, the court held that enforcement of the arbitral award would contravene the Russian public policy and dismissed the application for a writ of execution.
TRANSLATED BY AI
Original see here
Please open Telegram to view this post
VIEW IN TELEGRAM
German clothing manufacturer Ahlers AG (the Company) and its affiliated German entities had for many years supplied goods to Russian retailer Jeans Symphony LLC under import and supply agreements entered into in 2015.
In 2018, the parties recorded the Russian retailer’s outstanding debt in an Acknowledgment of Debt and Deferral Agreement. Performance of the contractual obligations was secured by guarantees provided by the beneficial owners of the German manufacturer’s business. One of the guarantors was a Russian citizen permanently residing in the United States (the applicant). The applicant also held a 10% interest in the Company’s Russian subsidiary, Ahlers Rus LLC. The guarantee issued by the applicant contained an arbitration clause in favor of the ICAC at the Chamber of Commerce and Industry of the Russian Federation.
In 2023, the Company was declared bankrupt in Germany due to adverse market conditions and the COVID-19 pandemic. The Bielefeld Local Court appointed Dr. Biner Bähr, a partner at the German office of White & Case, as insolvency administrator.
Following the failure to pay the debt under the guarantee, the insolvency administrator commenced arbitration before the ICAC at the Chamber of Commerce and Industry of the Russian Federation. In February 2026, the arbitral tribunal rendered an award in favor of the foreign creditor, ordering the applicant to pay more than EUR 500,000 in principal, interest at 7.5% per annum, as well as arbitration fees and legal costs exceeding EUR 83,000. Notably, two of the three arbitrators were nationals of “unfriendly” states.
The applicant applied to the Moscow Commercial Court to set aside the ICAC award. However, the court returned the application, finding that a dispute involving an individual who was not registered as an individual entrepreneur did not fall within the jurisdiction of Russian commercial courts.
The applicant appealed the first-instance ruling to the Moscow District Commercial Court. The insolvency administrator of the Company also supported the cassation appeal.
The Moscow Circuit Arbitrazh (Commercial) Court disagreed with the first-instance court and adopted the following legal position:
The courts did not examine the fact that the arbitration had been commenced by the insolvency administrator of a foreign company or that the dispute was connected with its insolvency proceedings.
Ultimately, the circuit court remitted the case to the first-instance court for reconsideration.
TRANSLATED BY AI
Original see here
Please open Telegram to view this post
VIEW IN TELEGRAM
The Memorandum aims to strengthen the position of international arbitration as the preferred method for resolving cross‑border disputes.
Under the Memorandum, the parties agreed to jointly organise events on international arbitration – by offline, hybrid, and online formats – to be held in Singapore and Brazil. Leading representatives of the arbitration community from both countries will be invited to participate.
The signing ceremony took place on 3 September 2026 in Rio de Janeiro. SIAC was represented by Ms. Adriana Uson, Director and Head of the North and South America division, and the FGV Chamber was represented by Ms. Juliana Loss, Executive Director.
TRANSLATED BY AI
Original see here
Please open Telegram to view this post
VIEW IN TELEGRAM
Entexol (the claimant), as subcontractor, and Sked (the respondent), as main contractor, entered into a contract for works on a Scottish power grid project (the contract).
The contract provided for the resolution of disputes arising thereunder by way of adjudication. During the performance of the contract, a dispute arose between the parties.
The claimant claimed the respondent to pay for the works carried out. In turn, the respondent filed a counterclaim for compensation of costs, on the ground that the claimant had missed the deadlines for completing the works. According to the respondent, the claimant failed to complete the works by a specific contractual completion date, which was set out in a direction sent to the claimant by email.
The adjudicator rejected the respondent's arguments, holding that time was not of the essence for the performance of the contract ("time was at large").
According to the adjudicator, there was no evidence that the claimant had agreed to any completion date. In particular, the email relied upon by the respondent could not be regarded as a binding direction on the completion date in the absence of the claimant's consent. A binding agreement on the completion date could not be imposed unilaterally by the respondent's direction.
As a result, under the adjudicator's decision, the respondent was ordered to pay the claimant approximately £114,000.
The claimant applied to the Court of Session in Scotland for enforcement of the adjudicator's decision. The respondent opposed enforcement, relying on breaches of the principles of natural justice. According to the respondent, the adjudicator had made a finding that time was at large when the parties had not raised that issue before him. As a result, the respondent was deprived of the opportunity to explain what it considered to be a "reasonable time" in the absence of a fixed date, while the adjudicator had acted "on a frolic of his own".
The judge held that the adjudicator's decision had been made without any breach, noting the following circumstances:
The judge thus granted the application for enforcement of the adjudicator's decision.
TRANSLATED BY AI
Original see here
Please open Telegram to view this post
VIEW IN TELEGRAM
www.bailii.org
Entexol LTD against Sked Construction LTD (Court of Session) [2026] CSOH 80 (25 August 2026)
The employee held the position of Chief Executive Officer at MetaCorp and held shares in the claimant pursuant to a share valuation agreement (the “Agreement”). Following his retirement, the employee was required to transfer the shares to MetaCorp, while MetaCorp was required to pay the employee compensation in return.
A dispute arose over the date for valuing the shares for the purposes of calculating the employee’s compensation. The employee argued that the relevant date was the end of the financial year preceding the termination of his employment, while MetaCorp maintained that it should be the end of the year in which the employment actually terminated.
The employee commenced arbitration under the Netherlands Arbitration Institute (NAI) Rules pursuant to the Agreement’s arbitration clause. The three-member tribunal comprised an arbitrator appointed by the employee from Curaçao, an arbitrator appointed by MetaCorp from the Netherlands, and a Dutch chair. The tribunal ultimately upheld the employee’s claims.
MetaCorp applied to the Hague Court of Appeal, as the court at the seat of arbitration, seeking to set aside the arbitral award on the following grounds:
The Court agreed with MetaCorp and noted that the arbitrator should have disclosed his business relationship with the employee and should have understood that MetaCorp could have had legitimate doubts as to his impartiality and independence. However, the Court did not consider this sufficient grounds for setting aside the award for the following reasons:
As regards MetaCorp’s arguments concerning interest, the Court held that the arbitral award had not come as a “surprise” to the parties. During the arbitration, the parties and the arbitral tribunal had discussed the issue. Accordingly, the parties could have expected that the arbitral tribunal might determine the commencement date for the accrual of interest in accordance with the applicable law. In line with established practice, the arbitral tribunal determined the commencement date for the accrual of interest as the date on which the arbitration was commenced.
Accordingly, the Hague Court of Appeal refused to set aside the NAI arbitral award.
TRANSLATED BY AI
Original see here
Please open Telegram to view this post
VIEW IN TELEGRAM
PJSC VTB (VTB) is the majority shareholder of German bank OWH SE i.L. (OWH), holding 99.39% of its shares. For many years, the parties entered into numerous foreign exchange and derivatives transactions. Following the events of February 2022 and the imposition of EU sanctions, the German financial regulator prohibited OWH from making any payments to, or disposing of assets in favor of, VTB Group entities in preparation for the bank’s subsequent liquidation.
In April 2022, the parties entered into a termination and settlement agreement (the Agreement), under which OWH undertook to pay VTB more than EUR 112 million. The parties agreed that their relationship would be governed by English law and that all disputes would be resolved by arbitration under the HKIAC Rules.
Despite the arbitration clause, VTB obtained a judgment in Russia in its favor pursuant to Article 248.1 of the Commercial Procedure Code of the Russian Federation and recovered more than EUR 19 million by enforcing against OWH’s assets in Russia. VTB also obtained an anti-suit injunction under Article 248.2 of the Commercial Procedure Code. As it is known, the dispute between VTB and OWH even reached the Constitutional Court of the Russian Federation, which, in a refusal decision, emphasized that Articles 248.1 and 248.2 of the Commercial Procedure Code should not be interpreted expansively.
In response to the breach of the arbitration agreement, OWH applied to the Hong Kong Court of First Instance seeking an anti-suit injunction. VTB opposed OWH’s application, relying on Article 19 of the Basic Law of Hong Kong, which excludes disputes concerning international relations and foreign policy from the jurisdiction of Hong Kong courts. Nevertheless, the court ruled in favor of OWH and granted the anti-suit injunction (the Judgment).
VTB appealed the Judgment to the Hong Kong Court of Appeal. In the appellate proceedings, OWH applied for security for costs in the amount of HKD 1.3 million, relying on the following circumstances:
VTB opposed OWH’s application on the following grounds:
The Hong Kong Court of Appeal upheld OWH’s position, reaching the following conclusions:
The Hong Kong Court of Appeal ordered VTB to provide security for costs in the amount of HKD 1.3 million.
TRANSLATED BY AI
Original see here
Please open Telegram to view this post
VIEW IN TELEGRAM
Telegram
Международный арбитраж
📍 Конституционный Суд РФ отказал в принятии жалобы OWH SE i.L. к рассмотрению, но прямо указал, что положения Закона Лугового не предусматривают автоматическое его применение: необходимо исследовать конкретные обстоятельства дела
В споре с «OWH SE i.L.»…
В споре с «OWH SE i.L.»…