Binaryx Platform Announcements
3.43K subscribers
564 photos
40 videos
537 links
Download Telegram
Only 3 hours left until the sales launch of ROOTS Villa 5!

• Expected yield — up to 29.8% APR in the first phase.
• ROI — 30.22%

🌍 ROOTS Villa 5 meets boutique hotel standards: every seam, every surface, every detail is designed for lasting beauty and tactile harmony.
Imagine Japanese precision combined with Balinese soul.

🏗 Construction standards and features:
• Foundation: deep reinforced concrete — stability on slopes, earthquake resistance.
• Frame: ironwood pillars + I-beam metal structure — steel strength, wood elegance.
• Walls: double brickwork with an air gap — thermal insulation, moisture protection, comfortable acoustics.
• Roof: Galvalume roofing with thermal insulation and an individual drainage system.
• Electrical & plumbing: certified under Indonesian standards, EU fittings, smart-system compatibility.

The developer provides:
• 10-year structural warranty.
• 1-year interior finishing warranty.

How to prepare for investment?
Top up your wallet in USDT (Polygon or Tron).
Use the top-up guide or contact support.
Set a reminder: July 17, 17:00 (Kyiv time).
Log in to the Binaryx platform → “Construction” section.
Refresh the page after the countdown and click “Invest.”

ROOTS Villa 5 Token Sale Launch
🗓️ July 17, 2025, Tuesday
🕗 17:00 UTC
🔥 ROOTS Villa 5 — NOW AVAILABLE ON THE BINARYX PLATFORM!

💎 Key Investment Highlights
Location: Ubud, Central Bali — a highly sought-after and rapidly growing area.
Ownership type: 29 + 10 years (leasehold).
ROI: up to 29% (in the first phase).
Completion date: July 22, 2026 (construction period — 13 months).

☝🏼 ROOTS Villa 5 is a private luxury residence within the ROOTS complex, nestled in the lush green heart of Ubud.

The architectural concept was brought to life by a team of renowned architects, including world-class studios and well-known Ukrainian designers — a collaborative effort that has created a harmonious and unique project.


🔗 Sales are open — invest now on the Binaryx platform!
🧱 Construction Update for Bali Balance Ocean Villas from the Developer

Progress on Villa №3 — Bali Balance
🔹 Active work on the final facade finishing: scaffolding installed, final layer of plaster being applied.
🔹 Roof waterproofing completed.
🔹 Ceilings and walls being prepared for final finishing.
🔹 Engineering systems installation almost completed.

💼 Invested: 66.03%
💰 APR: 21.45%


Progress on Villa №4 — Bali Balance
🔹 Electrical and low-voltage systems inspection completed.
🔹 Surfaces prepared for waterproofing, first layer applied.
🔹 Work on the usable roof underway: protective layers being installed.
🔹 Installation of air conditioning ducts started.

💼 Invested: 65.74%
💰 APR: 21.49%


Construction is moving forward confidently!
🚀 Don’t miss your chance to join and become a co-owner of a profitable investment in Bali!
3
ROOTS Villa 5 — first phase sold out in 10 minutes! 💸

▫️Yesterday we launched the sale of a new villa, and within the first 10 minutes, $145,000 was raised!

Here’s a reminder of the hottest projects currently open for your investment 🏗️

Bingin Magic Story Villa 3 — APR 20.6% / 65.3% funded
Bali Balance Ocean Villa 3 — APR 21.4% / 66.4% funded
Bali Balance Ocean Villa 4 — APR 21.4% / 66.0% funded

🔗 Choose the projects that match your investment strategy!
🏗 Construction Update: Bingin Magic Story

🔹 Foundation slab — completed
🔹 Waterproofing works — completed
🔹 Roof structure and carpentry works (including sirap) — completed
🔹 Steel structure — completed
🔹 Second-floor decking — completed
🔹 Plumbing works — completed. Stair materials have been ordered — assembly planned for this week
🔹 Electrical works — scheduled for completion next week
🔹 Red brick wall construction — ongoing, all materials are ready

💡 Interesting for investors:
Currently, the Bingin and Canggu areas are experiencing a noticeable increase in land value.
According to developers, the price of plots similar to those where the Bingin Magic Story project is being developed has risen from 14 million rupiah to approximately 46–50 million rupiah.

This once again confirms the high investment potential of this location.
🖇️ Interview with the developer
🖇️ More construction photos from Bingin available on the platform
👍1
New construction photos are now available on the platform 🏗️

Bingin Magic Story Villa 3
Bali Balance Ocean Villa 3
Bali Balance Ocean Villa 4
CASCADE Villa
CEMAGI
Mountain Retreat by Dukley
Oasis Royal Collection/NEXA
AWWA Hotel by Ribas
Ecoverse Suite

🔗 To see the updates, go to the project card, scroll down to the “Construction Progress” section, and check out the latest photos from June 2025.
Best Real Estate Investment Apps of 2025 (and Their Hidden Pitfalls) 🕵️‍♂️

In our new article, we dove deep into Google, sorted through the hype, uncovered the hidden traps, and gathered insights from real investors.

👉 What actually works? Where are the hidden risks? What do the developers prefer not to mention?

🔗 Read all about it in our new article!
Media is too big
VIEW IN TELEGRAM
PREDMET.CEMAGI — Construction Report from the Developer, July 2025

▫️ Concrete casting of the basement floor walls (Basement Floor) completed.
▫️ Ongoing earthworks, preparation of walls for waterproofing.
▫️ Preparation for septic system installation.
▫️ Installation of the basement floor slab underway in two stages.
▫️ Completion of ground floor walls and columns (Ground Floor) planned by August 14.
▫️ Installation of the ground floor slab planned by the end of August.

All work is proceeding on schedule.
2
This media is not supported in your browser
VIEW IN TELEGRAM
Construction Report PREDMET.CASCADE from the Developer

🏡 Villa 2
• Foundation completed, slab and walls planned for July.
• Pool already finished. Tiling in approximately 1.3 months.

🏡 Villa 3
• Foundation and slab ready, wall reinforcement in progress.
• Pool in the finishing stage. Tiling in approximately 1.4 months.

SUMMARY:
▫️ Pools have been poured.
▫️ Active wall casting and roof preparation underway.
▫️ Work is proceeding on schedule.
1
Bali Balance Ocean Villas 3 & 4 ~67% Already Funded!

Two designer villas in Bali, that have such competitive advantages:
✔️ A spacious living area (165 m²) situated on a land plot of 160 m², including a private pool of 16 m².
✔️ A terrace offering breathtaking views of the cliffs and surrounding forest.
✔️ A hilltop location where the complex harmoniously blends the four natural elements: water, air, earth, and sun.
✔️ 80-year leasehold for both villas — an exceptional advantage.
✔️ 10-year structural warranty and 5-year interior warranty.

• Bali Balance villa 3: APR 21,87%; ROI 9,57%
Bali Balance villa 4: APR 22%; ROI 9,63%

Construction quality highlights:
▫️ The foundation uses reinforced steel bars with a diameter of 16–19 mm, ensuring exceptional structural integrity
▫️ Floor slabs and interior walls are reinforced with 13–14 mm steel for added durability
▫️ A three-layer waterproofing system protects the villas from Bali’s tropical climate
▫️ Innovative wall design includes 10 cm air cavities for natural temperature and humidity control, reducing energy consumption


🗓 Completion is scheduled for Q4 2025.

• View the full villa overview here
• Or watch the video interview with the developer

📈 Rising demand and a prime location — everything an investor is looking for!
1
Bingin Magic Story by Rumah Archipelago Villas is a boutique complex of seven designer two-story villas, each spanning 115 m².

The project combines modern industrial loft aesthetics with traditional Balinese elements.
High ceilings with Bangkirai wood beams, panoramic windows, and open floor plans create a space filled with light, air, and tranquility.

📍 Bingin Beach — one of Bali’s favorite spots for surfers and tourists — is just a short walk away.
• 30–40 minutes to the international airport
• 15–20 minutes to the island’s most popular attractions

Already invested: 67%
💸 APR: 21.15%


🔍 What makes these villas unique?
▪️ A rare blend of Balinese authenticity and loft-style elegance
▪️ Two-story fireplace, open-air bathtub, and hidden loggia
▪️ Durable, weather-resistant materials adapted to tropical conditions
▪️ Reinforced steel frame (200 mm thick) — built to last
▪️ Open layout and bold designer touches for maximum visual impact


🎥 Watch the developer interview to discover:
• What makes Bingin Magic Story stand out
• How it differs from other projects
• What kind of returns investors can expect

🔗 Read the full project overview or
🖇️ investing now!
👍1
💡 Binaryx Platform Updates — July 2025

In July, the Binaryx team completed significant work on product development and technical improvements. Here are the key highlights of the month:

🔹 AWWA Hotel: First investment strategy successfully implemented
🔹 DAO Voting Closed: Mountain Retreat by Dukley
🔹 Internal Improvements: Bug fixes, UI updates, and overall platform optimization

📖 Read more in our latest article.

Thank you for staying with us and helping shape the new era of real estate investing with Binaryx!
🔥3
Media is too big
VIEW IN TELEGRAM
🏗️ Taryan Dragon Construction Update — July 2025

Construction is progressing steadily. In July, the developer’s team reached several key milestones:
RW2 — Concreting completed.
RW3 & RW4 — Ongoing work on both retaining walls.
Earthworks — 38,000 m³ of soil removed out of the planned 43,000 m³.
RW3 & RW4 — Concrete pouring in progress.
RW3 & RW4 — Concreting completed across both segments.