/var/log/DMIT-NOC.log
We will gradually transfer your VM from the stand-alone storage file system to our Ceph HA storage. DMIT LAX cluster used the zfs file system which allows us to live to migrate your disk fille to Ceph. There should have only an IO delay during migration…
LAX-81403SR needs to be rebooted.
ETA: 30mins
We found some disks in this server is not work well.
ETA: 30mins
We found some disks in this server is not work well.
LAX Ceph migration is closed to full completion.
The IOPS limit of LAX VM will be tripled; the burstable IOPS be increased to six times than now after Ceph migration completion.
HKG is waiting for our on-site engineer to install RAM and SSD to another 2 servers.
Once we finished the migration, the IOPS limit will be doubled, and the burstable IOPS will be quadrupled.
80% of HKG VM already be migrated to AMD EPYC node and Ceph and running well.
The IOPS limit of LAX VM will be tripled; the burstable IOPS be increased to six times than now after Ceph migration completion.
HKG is waiting for our on-site engineer to install RAM and SSD to another 2 servers.
Once we finished the migration, the IOPS limit will be doubled, and the burstable IOPS will be quadrupled.
80% of HKG VM already be migrated to AMD EPYC node and Ceph and running well.
/var/log/DMIT-NOC.log
LAX Ceph migration is closed to full completion. The IOPS limit of LAX VM will be tripled; the burstable IOPS be increased to six times than now after Ceph migration completion. HKG is waiting for our on-site engineer to install RAM and SSD to another 2…
We complete almost all tasks for LAX, due to disk cache mode change and the ceph cluster performance improvement needed.
DMIT NOC will reboot some nodes / VMs at Oct 27 4PM(EST).
After this action, all tasks are complete.
DMIT NOC will reboot some nodes / VMs at Oct 27 4PM(EST).
After this action, all tasks are complete.
/var/log/DMIT-NOC.log
We complete almost all tasks for LAX, due to disk cache mode change and the ceph cluster performance improvement needed. DMIT NOC will reboot some nodes / VMs at Oct 27 4PM(EST). After this action, all tasks are complete.
LAX Completed.
Testing VM:
vCore: 1Core
vRAM: 1GB
vDisk: 20G via Ceph
NO IOPS restrictions on testing VM = reference only; each products have different IOPS limits.
Testing VM:
vCore: 1Core
vRAM: 1GB
vDisk: 20G via Ceph
NO IOPS restrictions on testing VM = reference only; each products have different IOPS limits.
/var/log/DMIT-NOC.log
We complete almost all tasks for LAX, due to disk cache mode change and the ceph cluster performance improvement needed. DMIT NOC will reboot some nodes / VMs at Oct 27 4PM(EST). After this action, all tasks are complete.
We also found another tiny issue. You can ignore it if you don't care about #IO_Latency
Please install ioping on your VM by:
YUM based
If ioping is not found, please do
APT based:
Please reinstall the system if you found the latency over than 900us and you care about it.
Please install ioping on your VM by:
YUM based
yum install iopingioping /dev/vda1If ioping is not found, please do
yum install epel-releaseAPT based:
apt install iopingioping /dev/vda1Please reinstall the system if you found the latency over than 900us and you care about it.
/var/log/DMIT-NOC.log
There are already over 400+ VM running well in our HKG EPYC with the Ceph cluster. Your data will be live migrated to the Ceph HA cluster and AMD node. Please try to backup your data to prevent any unexpected event. As we expected, it is smooth progress.…
HKG Completed.
The IO Latency suggestion above also works for the HKG location.
The IO Latency suggestion above also works for the HKG location.
The maintenance recent for HKG and LAX has been completed.
Thanks for your patience
Please read the #IO_Latency above, it works for HKG and LAX.
Thanks for your patience
Please read the #IO_Latency above, it works for HKG and LAX.
/var/log/DMIT-NOC.log pinned «The maintenance recent for HKG and LAX has been completed. Thanks for your patience Please read the #IO_Latency above, it works for HKG and LAX.»
Email copy:
Notice of Completion of High Reliability Reconstruction
DMIT NOC made a reconstruction for our LAX and HKG datacenter recently.
- DMIT upgrades all racks in HKG and LAX to 2 switches with vPC configuration. It improved the redundancy to avoid single device error like transceiver or switch failure.
- DMIT swapped from ZFS to the Ceph Cluster solution. It helps to avoid single-node failure, like some cases we had in HKG before.
- DMIT joined the AMD EPYC family in both HKG and LAX locations. All DMIT Hyper servers are powered by AMD EPYC 2nd GEN.
The route-map of DMIT:
- New location launch
- Move to DMIT self-developed client area system.
-- Simple UI;
-- Batter task performance
-- Client self-service BGP support
-- Client self-service rDNS support
-- HA support (current DMIT only offer High Reliability)
- etc..
Thanks to all DMIT clients for the support and trust us.
Notice of Completion of High Reliability Reconstruction
DMIT NOC made a reconstruction for our LAX and HKG datacenter recently.
- DMIT upgrades all racks in HKG and LAX to 2 switches with vPC configuration. It improved the redundancy to avoid single device error like transceiver or switch failure.
- DMIT swapped from ZFS to the Ceph Cluster solution. It helps to avoid single-node failure, like some cases we had in HKG before.
- DMIT joined the AMD EPYC family in both HKG and LAX locations. All DMIT Hyper servers are powered by AMD EPYC 2nd GEN.
The route-map of DMIT:
- New location launch
- Move to DMIT self-developed client area system.
-- Simple UI;
-- Batter task performance
-- Client self-service BGP support
-- Client self-service rDNS support
-- HA support (current DMIT only offer High Reliability)
- etc..
Thanks to all DMIT clients for the support and trust us.
DMIT HKG IP re-arrange notice:
We will arrange you a new IP address if your IP is in the below subnet:
103.135.248.0/24
103.135.249.0/24
103.135.250.0/24
103.135.251.0/24
There are lots of unused IPs in these subnets; to improve usability and to offer different types of services. We will need to swap your IP to a new one. You will receive a ticket and email for the detail of the rearranging.
We will arrange you a new IP address if your IP is in the below subnet:
103.135.248.0/24
103.135.249.0/24
103.135.250.0/24
103.135.251.0/24
There are lots of unused IPs in these subnets; to improve usability and to offer different types of services. We will need to swap your IP to a new one. You will receive a ticket and email for the detail of the rearranging.
Thanks for all client's support on our PVM.HKG.Lite services.
The hardware resource in HK is closed to be used up soon.
DMIT ordered 4 more sets of EPYC nodes today. It will be ready to use within 3 weeks. 🥳
The hardware resource in HK is closed to be used up soon.
DMIT ordered 4 more sets of EPYC nodes today. It will be ready to use within 3 weeks. 🥳
As the order quantity of PVM.HKG.Lite over than our expectations
DMIT NOC needs to reboot some nodes in Hong Kong to upgrade the hardware configuration.
ETA: 30mins per nodes, your VM will down 10mins (up to 1 hour)
Because it's emergency maintenance, we are still waiting for the delivery of hardware; it's not able to give a confirmed time
Date/Time:
Hong Kong Time;
Between Nov 13, 6 P.M and Nov 16, 10 P.M.
DMIT NOC needs to reboot some nodes in Hong Kong to upgrade the hardware configuration.
ETA: 30mins per nodes, your VM will down 10mins (up to 1 hour)
Because it's emergency maintenance, we are still waiting for the delivery of hardware; it's not able to give a confirmed time
Date/Time:
Hong Kong Time;
Between Nov 13, 6 P.M and Nov 16, 10 P.M.
DMIT NOC needs to reboot some nodes in Los Angeles to upgrade the hardware configuration.
ETA: 30mins per nodes, your VM will down 20 mins (up to 1 hour)
Date/Time:
Pacific Standard Time;
Nov 17, 3:00 P.M ~ 5:00 P.M
ETA: 30mins per nodes, your VM will down 20 mins (up to 1 hour)
Date/Time:
Pacific Standard Time;
Nov 17, 3:00 P.M ~ 5:00 P.M
/var/log/DMIT-NOC.log pinned «DMIT NOC needs to reboot some nodes in Los Angeles to upgrade the hardware configuration. ETA: 30mins per nodes, your VM will down 20 mins (up to 1 hour) Date/Time: Pacific Standard Time; Nov 17, 3:00 P.M ~ 5:00 P.M»
/var/log/DMIT-NOC.log
DMIT NOC needs to reboot some nodes in Los Angeles to upgrade the hardware configuration. ETA: 30mins per nodes, your VM will down 20 mins (up to 1 hour) Date/Time: Pacific Standard Time; Nov 17, 3:00 P.M ~ 5:00 P.M
All maintenance operations have been completed; Sorry for delay.